In U.S. Pipeline, Inc. v Northern Natural Gas Company, 303 Neb. 444 (2019) the Nebraska Supreme Court issued a concerning consequential and liquidated damages.
Northern’s argument that U.S. Pipeline cannot avoid liquidated damages because it neglected to request additional time on its change orders is unfounded. By requesting the Extra Work, submitting the designs after the passing of the substantial completion date, and further failing to inform U.S. Pipeline that it intended to enforce the liquidated damages provision in the contract, Northern manifested a clear intent to waive the contractual liquidated damages provision. Northern knowingly requested Extra Work that would clearly exceed the substantial completion date. The district court’s determination that Northern’s conduct amounted to a waiver was supported by the evidence and cannot be said to be clearly wrong.
In the midst of a construction project, it is important to ensure that change orders address the completion date of the project. Costs related to change orders will be “direct damages” which are not waived even if consequential damages have been waived in the agreement.
Angela Madathil is happy to assist project owners with projects in Nebraska, Kansas, or Missouri review their construction agreement, and assist with compliance with the contract during projects.
Angela Madathil is a Nebraska Construction Attorney and provides legal assistance to Contractors, Roofing Companies, Siding Companies, Architects, and Engineers in Nebraska, Missouri, and Kansas. This can involve contract review and negotiation, ongoing contract guidance during a project, and risk mitigation when issues arise. The Goosmann Law Firm team advises Contractors, Architects, and Engineers throughout the Midwest and has attorneys licensed in Iowa, Kansas, Minnesota, Missouri, Nebraska, South Dakota, and other states.